Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Wed May 02, 2018 9:53 am
by EBG
250 East Tce. This project was proposed sometime around March/Apr 2016 and was approved late 2016. The project started Jan/Feb 2017 when they dug out the basement, so it has taken 16 months to get to this stage. There is usually only 3 or 4 people working on site, (5 is a crowd). (The Barcelona Cathedral which started in 1916 is now making faster progress). Pictures 25 Feb start of digging basement and excavation finished 12 March 2017.

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Wed May 02, 2018 11:17 am
by how good is he
The rumour I have heard is the owner who I think is also the builder hasn't got the construction finance approved but is using his own money to [slowly] start construction and I assume to stimulate sales and get finance approval. Which I guess is better than just having the empty piece of land just sitting there? It also may help to comply with the planning/building approval without needing to seek an extension?

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Wed May 02, 2018 11:39 am
by wilkiebarkid
EBG wrote:
Wed May 02, 2018 9:53 am
250 East Tce. This project wad proposed sometime around March/Apr 2016 and was approved late 2016. The project started Jan/Feb 2017 when they dug out the basement, so it has taken 16 months to get to this stage. There is usually only 3 or 4 people working on site, (5 is a crowd). (The Barcelona Cathedral which started in 1916 is now making faster progress). Pictures 25 Feb start of digging basement and excavation finished 12 March 2017.
???

There is a crane erected and the construction of this is well and truly above basement level!!

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Wed May 02, 2018 3:05 pm
by EBG
yes. I meant it has taken 16 months to get to putting up the steel for the ground floor

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Wed May 02, 2018 6:19 pm
by Algernon
If the development was half as good as Sagrada Familia they can have 100 years to build it if need be :lol:

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Fri May 04, 2018 5:47 pm
by EBG
CBC new school bldg. 212 Wakefield St. Pictures 4 May 2018

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Fri May 04, 2018 10:15 pm
by EBG
Update 4/5/2018 apartments at 69 Queen St (between Carrington St and Halifax St Adelaide). This project is nearly complete apart from some minor painting and glass for balcony balustrades.

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Tue May 08, 2018 11:41 pm
by EBG
Piling has finished for the 9 level apartment building at 12 Tapley St just off Gilbert Street and the footings are being worked on. Picture 8/5/2018

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Sun May 27, 2018 7:58 pm
by EBG
The back 1/2 of the footings has been concreted and the front 1/2 (nearest Tapleys St) is still to be completed. The service core is in the centre where all the timber is. At 9 stories I don't know whether this site will get a tower crane or not. Picture 27/5/2018.

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Sun Jun 03, 2018 2:55 pm
by EBG
Sunday 3/6/2018 - 12 Tapley St the footings are complete and the first columns are being formed up.

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Sat Jun 16, 2018 11:21 pm
by EBG
12 Tapley St, off Gilbert St. The ground floor is nearly complete. picture 16/6/2018.

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Mon Jun 18, 2018 4:35 pm
by EBG
250 East Tce. Work has finally started on level 2 on this project . There were at least 7 workers on site today 18/6/2018.

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Tue Jun 19, 2018 11:24 pm
by EBG
St Mary's College new School building Corner of Franklin St & West Tce. 19/6/2018

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Tue Jun 19, 2018 11:26 pm
by EBG
Plus the other picture. Notice the diagonal wind bracing in the roof level.

Re: News & Discussion: Low/Mid-Rise CBD Development

Posted: Mon Jun 25, 2018 4:31 pm
by EBG
250 East Tce has finally picked up the pace with concrete wall panels being craned in today.