[U/C] M2 North-South Motorway
- ChillyPhilly
- Super Size Scraper Poster!
- Posts: 2591
- Joined: Sun Dec 07, 2008 11:35 pm
- Location: Kaurna Land.
- Contact:
[U/C] Re: News & Discussion: South Road / North-South Corridor
Here they are rotated and cropped.
Our state, our city, our future.
All views expressed on this forum are my own.
All views expressed on this forum are my own.
[U/C] Re: News & Discussion: South Road / North-South Corridor
If that's true its pretty lazy and could lead to mis-communication with the public which is something youd think they'd be keen to avoid.
Big infrastructure investments are usually under-valued and & over-criticized while in the planning stage. It's much easier to envision the here and now costs and inconveniences, and far more difficult to imagine fully the eventual benefits.
[U/C] Re: News & Discussion: South Road / North-South Corridor
Sorry, but ... bollocks.mawsonguy wrote: ↑Tue Feb 27, 2018 10:48 pmOff ramps are designed with curves in order to slow traffic. There is insufficient room between the back fence of the caravan park and the southbound carriageway to accommodate an S bend in the offramp which means it cannot connect with a roundabout on the overpass. Likewise, there is insufficient room between the overpass and the southern boundary of the caravan park to allow the offramp to merge with the eastbound carriageway on the overpass.
Take a look at the newest freeway interchange in South Australia, which was built last year - the Nairne exit on the South Eastern Freeway. When exiting from the Murray Bridge direction, the ramp is steep (downhill) and almost straight, with a roundabout at the bottom. When exiting from the Adelaide end the ramp does an almost 180-degree turn, and is very tight. No problems so far, and heaps of use.
cheers,
Rhino
Rhino
- ChillyPhilly
- Super Size Scraper Poster!
- Posts: 2591
- Joined: Sun Dec 07, 2008 11:35 pm
- Location: Kaurna Land.
- Contact:
[U/C] Re: News & Discussion: South Road / North-South Corridor
Work on rebuilding the Pym Street/South Road intersection is well underway.
At the opposite end of the project, work has again picked up on Taylors Bridge (over the Torrens).
At the opposite end of the project, work has again picked up on Taylors Bridge (over the Torrens).
Our state, our city, our future.
All views expressed on this forum are my own.
All views expressed on this forum are my own.
[U/C] Re: News & Discussion: South Road / North-South Corridor
Port Road intersection same on both ends of the bridge.
- ChillyPhilly
- Super Size Scraper Poster!
- Posts: 2591
- Joined: Sun Dec 07, 2008 11:35 pm
- Location: Kaurna Land.
- Contact:
[U/C] Re: News & Discussion: South Road / North-South Corridor
Torrens to Torrens Updates
- March 2018 Construction Newsletter http://www.t2talliance.com.au/wp88/wp-c ... h-2018.pdf
From the final page:
'A Community Information Drop In Day and sausage sizzle will be held on Saturday 14 April from 11am to 2pm at the T2T Alliance Project site office on Ridley Street, Hindmarsh. (Please note that there is limited parking available on Ridley Street).
Come along anytime between 11am and 2pm to meet members of the team and find out more about:
• works in progress, including the lowered motorway construction
• remaining works, including landscaping.
Team members will be available to answer questions about the project and there will be an opportunity to view video footage of the lowered motorway works in progress, as well as photos of key construction activities.'
- March 2018 Pym Street intersection update, featuring final layout design (rudimentary, but it's intended to just show the traffic movements): http://www.t2talliance.com.au/wp88/wp-c ... h-2017.pdf
- March 2018 Construction Newsletter http://www.t2talliance.com.au/wp88/wp-c ... h-2018.pdf
From the final page:
'A Community Information Drop In Day and sausage sizzle will be held on Saturday 14 April from 11am to 2pm at the T2T Alliance Project site office on Ridley Street, Hindmarsh. (Please note that there is limited parking available on Ridley Street).
Come along anytime between 11am and 2pm to meet members of the team and find out more about:
• works in progress, including the lowered motorway construction
• remaining works, including landscaping.
Team members will be available to answer questions about the project and there will be an opportunity to view video footage of the lowered motorway works in progress, as well as photos of key construction activities.'
- March 2018 Pym Street intersection update, featuring final layout design (rudimentary, but it's intended to just show the traffic movements): http://www.t2talliance.com.au/wp88/wp-c ... h-2017.pdf
Our state, our city, our future.
All views expressed on this forum are my own.
All views expressed on this forum are my own.
[U/C] Re: News & Discussion: South Road / North-South Corridor
regarding the works around the Northern Connector Southern interchange on PREXY.. heading west from South Road, the median Strip has been excavated down about half a metre.. does anyone have an idea why?
Is it for lighting around the future I/C?
Is it for lighting around the future I/C?
Big infrastructure investments are usually under-valued and & over-criticized while in the planning stage. It's much easier to envision the here and now costs and inconveniences, and far more difficult to imagine fully the eventual benefits.
- ChillyPhilly
- Super Size Scraper Poster!
- Posts: 2591
- Joined: Sun Dec 07, 2008 11:35 pm
- Location: Kaurna Land.
- Contact:
[U/C] Re: News & Discussion: South Road / North-South Corridor
Not sure about the depth, but removing electrical cabling could be why. That stretch of PRExy will be widened to accommodate the interchange and its new lanes and ramps.
Our state, our city, our future.
All views expressed on this forum are my own.
All views expressed on this forum are my own.
[U/C] Re: News & Discussion: South Road / North-South Corridor
The Darlington Project team have also released a newsletter: https://www.infrastructure.sa.gov.au/__ ... web_v2.pdf
Here are the upcoming milestones:
1st quarter of 2018
Ayliffes Road traffic switch
Installation of concrete beams for the Flinders Drive bridge
Concrete pours for Flinders Drive bridge deck
Excavation for bridge enabling works
2nd quarter of 2018
Installation of concrete beams for the Sturt Road bridge
Excavation works
Main South Road bridge over the Southern Expressway to surface roads open to traffic
Installation of Main South Road bridge over the Southern Expressway to the lowered motorway
South Road Traffic switch (between Ayliffes Road and Tonsley Boulevard)
Traffic switch between Southern Expressway and Flinders Drive
3rd quarter of 2018
Flinders Drive Extension (new road between Sturt Road and Flinders Drive) open to traffic
Excavation works
Birch Crescent/Sturt Road signalised intersection completed and operational
Installation of Ayliffes Road bridge
Traffic switch between Southern Expressway and Flinders Drive
Completion of Flinders Drive bridge
4th quarter of 2018
Installation of concrete beams for the Tonsley Boulevard bridge
Excavation works
Completion of Sturt Road bridge
Completion of Sutton Road/Mimosa Drive bridge
Here are the upcoming milestones:
1st quarter of 2018
Ayliffes Road traffic switch
Installation of concrete beams for the Flinders Drive bridge
Concrete pours for Flinders Drive bridge deck
Excavation for bridge enabling works
2nd quarter of 2018
Installation of concrete beams for the Sturt Road bridge
Excavation works
Main South Road bridge over the Southern Expressway to surface roads open to traffic
Installation of Main South Road bridge over the Southern Expressway to the lowered motorway
South Road Traffic switch (between Ayliffes Road and Tonsley Boulevard)
Traffic switch between Southern Expressway and Flinders Drive
3rd quarter of 2018
Flinders Drive Extension (new road between Sturt Road and Flinders Drive) open to traffic
Excavation works
Birch Crescent/Sturt Road signalised intersection completed and operational
Installation of Ayliffes Road bridge
Traffic switch between Southern Expressway and Flinders Drive
Completion of Flinders Drive bridge
4th quarter of 2018
Installation of concrete beams for the Tonsley Boulevard bridge
Excavation works
Completion of Sturt Road bridge
Completion of Sutton Road/Mimosa Drive bridge
-
- High Rise Poster!
- Posts: 297
- Joined: Sat Mar 11, 2006 1:02 am
- Location: Adelaide (Hallett Cove)
[U/C] Re: News & Discussion: South Road / North-South Corridor
does anyone know what's happening with the section of south road between Pym street and the start of the superway after recency road? the T2T finishes at Pym street then a km or so down the road the superway starts. are there any plans for this section in between?
- ChillyPhilly
- Super Size Scraper Poster!
- Posts: 2591
- Joined: Sun Dec 07, 2008 11:35 pm
- Location: Kaurna Land.
- Contact:
[U/C] Re: News & Discussion: South Road / North-South Corridor
That section is a separate project. We'll have to wait and see what happens.aceman wrote:does anyone know what's happening with the section of south road between Pym street and the start of the superway after recency road? the T2T finishes at Pym street then a km or so down the road the superway starts. are there any plans for this section in between?
Our state, our city, our future.
All views expressed on this forum are my own.
All views expressed on this forum are my own.
-
- High Rise Poster!
- Posts: 297
- Joined: Sat Mar 11, 2006 1:02 am
- Location: Adelaide (Hallett Cove)
[U/C] Re: News & Discussion: South Road / North-South Corridor
ok thanks, I've noticed that if the T2T was to continue further north towards recency rd there are a few large showrooms etc near the intersection of recency rd. further south there's mainly houses and u can see where the land acquisition suddenly stopped!!
[U/C] Re: News & Discussion: South Road / North-South Corridor
Money from the state government has been allocated in last year's budget, so hopefully there will be some federal funding for this in the next federal budget.aceman wrote: ↑Sat Mar 31, 2018 9:15 pmdoes anyone know what's happening with the section of south road between Pym street and the start of the superway after recency road? the T2T finishes at Pym street then a km or so down the road the superway starts. are there any plans for this section in between?
[U/C] Re: News & Discussion: South Road / North-South Corridor
Given the latest 2PP at federal level I'm confident that we will get fundingNorman wrote:Money from the state government has been allocated in last year's budget, so hopefully there will be some federal funding for this in the next federal budget.aceman wrote: ↑Sat Mar 31, 2018 9:15 pmdoes anyone know what's happening with the section of south road between Pym street and the start of the superway after recency road? the T2T finishes at Pym street then a km or so down the road the superway starts. are there any plans for this section in between?
[U/C] Re: News & Discussion: South Road / North-South Corridor
Well the Liberals(state) are also committed to the north south corridor, so they say. It was an election year..Waewick wrote: ↑Mon Apr 02, 2018 6:54 pmGiven the latest 2PP at federal level I'm confident that we will get fundingNorman wrote:Money from the state government has been allocated in last year's budget, so hopefully there will be some federal funding for this in the next federal budget.aceman wrote: ↑Sat Mar 31, 2018 9:15 pmdoes anyone know what's happening with the section of south road between Pym street and the start of the superway after recency road? the T2T finishes at Pym street then a km or so down the road the superway starts. are there any plans for this section in between?
Hopefully we can get a 'rolling' works program for the remainder of the corridor now. Once work finishes on one section, the next section is ready to go and they move on to that without too much delay.
Who is online