[U/C] M2 North-South Motorway

Threads relating to transport, water, etc. within the CBD and Metropolitan area.
Message
Author
kymbosa
High Rise Poster!
Posts: 113
Joined: Mon Aug 06, 2007 4:39 pm

[U/C] Re: M2 North-South Motorway

#4516 Post by kymbosa » Mon Apr 20, 2020 5:52 am

The split of the Sexy is so traffic using South Road coming on to the lower deck won’t need to merge across five lanes.

The split allows Sexy traffic to already be in the correct lanes, if heading to the “eastern suburbs” (as per the sign), or the city, by being on the eastern side of the second bridge.

This also means traffic coming from South Road, won’t need to navigate over multiple lanes when they arrive at the lower deck, as they should be already in the correct lane to drive towards Goodwood or the city before the bridge.

Once the lower deck in that section moves to 5 lanes, at 80km/h than it is safer to spilt the traffic like this than have it merge in a traditional sense.

The spilt traffic is how in the UK and Europe they create free flowing highways and less traffic trying to change lanes at the last minute; which is a SA speciality, oh I need to go to Goodwood, oh well let’s just change from the right hand lane over to the left hand lane at the last minute. Lol.

neoballmon
Legendary Member!
Posts: 522
Joined: Sun Aug 26, 2012 10:54 am
Location: Morphett Vale

[U/C] [U/C] Re: [U/C] Re: M2 North-South Motorway

#4517 Post by neoballmon » Tue Apr 21, 2020 12:57 pm


kymbosa wrote:
The spilt traffic is how in the UK and Europe they create free flowing highways and less traffic trying to change lanes at the last minute; which is a SA speciality, oh I need to go to Goodwood, oh well let’s just change from the right hand lane over to the left hand lane at the last minute. Lol.
10 years after completion, i still see people in the right lane of South Road have that "oh shit!" Moment when they realise they need to be in the left lane for Anzac highway. So this will be fun for many years to come.

Looking forward to a free-flowing Adelaide!

Bacon
High Rise Poster!
Posts: 117
Joined: Tue Oct 15, 2013 1:17 pm

[U/C] Re: M2 North-South Motorway

#4518 Post by Bacon » Fri Apr 24, 2020 7:41 pm

Some drone shots from the R2P site

https://r2palliance.com.au/resources/gallery

Image
Image
Image
Image
Image
Image
Image

ml69
Legendary Member!
Posts: 993
Joined: Mon Jan 03, 2011 11:16 pm
Location: Adelaide SA

[U/C] Re: M2 North-South Motorway

#4519 Post by ml69 » Fri Apr 24, 2020 11:17 pm

Wow!

NTRabbit
High Rise Poster!
Posts: 364
Joined: Fri Dec 28, 2018 10:00 pm

[U/C] Re: M2 North-South Motorway

#4520 Post by NTRabbit » Sat Apr 25, 2020 10:32 pm

So are the Mattress King and those old sawtooths going to be demolished too, or is the whole project curving around that estate?

User avatar
Norman
Donating Member
Donating Member
Posts: 6391
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: M2 North-South Motorway

#4521 Post by Norman » Sun Apr 26, 2020 3:07 am

NTRabbit wrote:
Sat Apr 25, 2020 10:32 pm
So are the Mattress King and those old sawtooths going to be demolished too, or is the whole project curving around that estate?
Just like the substation at Port Road, the motorway will veer around it towards the east.

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6029
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: M2 North-South Motorway

#4522 Post by rev » Mon Apr 27, 2020 12:27 pm

So when R2P is done, we will have about 48km of non-stop motorway/freeway in the northern/western side of Adelaide and another 20km down south, along with 76km of the SEF. Leaving about 11km for the NS corridor.

Another few decades, and someone in power will have their lightbulb moment and connect the NSM to the SEF.
Decades after that and someone else will have their lightbulb moment and say we need a ring route.

By the time we finally finish building it all, I fully expect other major cities in this country to have implemented star trek technology and beam shit around.

marbles
Gold-Member ;)
Posts: 62
Joined: Sun Feb 23, 2020 4:22 pm

[U/C] Re: M2 North-South Motorway

#4523 Post by marbles » Mon Apr 27, 2020 2:09 pm

Norman wrote:
Sun Apr 26, 2020 3:07 am
NTRabbit wrote:
Sat Apr 25, 2020 10:32 pm
So are the Mattress King and those old sawtooths going to be demolished too, or is the whole project curving around that estate?
Just like the substation at Port Road, the motorway will veer around it towards the east.

remaining...
https://www.youtube.com/watch?v=llGKcge ... e=emb_logo

Waewick
Super Size Scraper Poster!
Posts: 3620
Joined: Tue Jun 10, 2008 1:39 pm

[U/C] Re: [U/C] Re: M2 North-South Motorway

#4524 Post by Waewick » Sun May 03, 2020 11:43 pm


rev wrote:
By the time we finally finish building it all, I fully expect other major cities in this country to have implemented star trek technology and beam shit around.
Image,

User avatar
Norman
Donating Member
Donating Member
Posts: 6391
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: M2 North-South Motorway

#4525 Post by Norman » Fri May 08, 2020 1:28 pm

Not sure how old this is, but it just popped up on my feed
Tender released for early works on final section of North-South Corridor
Posted on May 8, 2020 by Lauren Jones

An Executive Director has been appointed to oversee what will be South Australia’s biggest infrastructure project, the final 10.5 kilometres on the North South Corridor.

A $3 million tender has been released to engage geotechnical experts to perform investigation works that will determine the final stage of the North-South Corridor.

Susana Fueyo will become Executive Director of the North-South Corridor Program Delivery Office (PDO), overseeing the final stage of the major project.

Ms. Fueyo is the Program Director at Major Road Projects Victoria, where she oversees a $4 billion portfolio of infrastructure works.
Full story: https://www.roadsonline.com.au/tender-r ... -corridor/

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6029
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: M2 North-South Motorway

#4526 Post by rev » Fri May 08, 2020 1:50 pm

Time frame for it?

User avatar
Norman
Donating Member
Donating Member
Posts: 6391
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: M2 North-South Motorway

#4527 Post by Norman » Fri May 08, 2020 3:37 pm

rev wrote:
Fri May 08, 2020 1:50 pm
Time frame for it?
The technical investigation works? 12 months according to the article.
The State Government is now seeking to engage an expert company to undertake the $3 million investigation works over the next 12 months.

Vasco
High Rise Poster!
Posts: 129
Joined: Wed Jul 11, 2018 9:02 pm

[U/C] Re: M2 North-South Motorway

#4528 Post by Vasco » Fri May 08, 2020 3:44 pm

Didn’t Knoll say they’d have the answer to what general form the final stage would take by end of 2019?

Now we have to wait a further 12 months?


Sent from my iPhone using Tapatalk

User avatar
Spotto
Legendary Member!
Posts: 693
Joined: Wed May 15, 2019 9:05 pm

[U/C] Re: M2 North-South Motorway

#4529 Post by Spotto » Fri May 08, 2020 4:22 pm

This was one of their main election promises. They've been in power for 2 years touting how they're going to build a tunnel (or two separate tunnels) and they're only just now appointing geological experts? What have they been doing for the last 2 years?

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6029
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: M2 North-South Motorway

#4530 Post by rev » Fri May 08, 2020 4:34 pm

Norman wrote:
Fri May 08, 2020 3:37 pm
rev wrote:
Fri May 08, 2020 1:50 pm
Time frame for it?
The technical investigation works? 12 months according to the article.
The State Government is now seeking to engage an expert company to undertake the $3 million investigation works over the next 12 months.
Cool. I thought what was posted was the whole thing, didn't bother to click the link.