[U/C] Re: North-South Motorway

#2971 Post by Ser Noit of Loit » Sun Sep 02, 2018 10:56 pm

aaronjameslange wrote:
Sat Sep 01, 2018 7:27 am
Hooligan wrote:
Fri Aug 31, 2018 6:36 pm
Any word on when T2T will open?
From a news.com.au article dated Jan 9:

THE Torrens to Torrens upgrade of South Rd will be finished by the end of September, three months ahead of schedule.
The new roadway will open earlier than expected and come in $95 million under the originally forecast $896 million budget, Transport and Infrastructure Minister Stephen Mullighan said on Tuesday.

"This project was due to be completed by the very end of 2018, the end of this year. Now the estimated completion date is by the end of September,” Mr Mullighan said.
Can we get these guys to work on the tram line?

User avatar
[Shuz]
Super Size Scraper Poster!
Posts: 3211
Joined: Sun Apr 10, 2011 5:26 pm

[U/C] Re: North-South Motorway

#2972 Post by [Shuz] » Mon Sep 03, 2018 4:29 pm

Apparently $1.2b has been earmarked for the Torrens to Anzac section of NS corridor has part of Liberals reelection campaign according to leaked documents to news.com.au
Any views and opinions expressed are of my own, and do not reflect the views or opinions of any organisation of which I have an affiliation with.

aceman
High Rise Poster!
Posts: 297
Joined: Sat Mar 11, 2006 1:02 am
Location: Adelaide (Hallett Cove)

[U/C] Re: North-South Motorway

#2973 Post by aceman » Mon Sep 03, 2018 9:21 pm

is that state funding?

SBD
Super Size Scraper Poster!
Posts: 2526
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[U/C] Re: North-South Motorway

#2974 Post by SBD » Mon Sep 03, 2018 9:24 pm

aceman wrote:
Mon Sep 03, 2018 9:21 pm
is that state funding?
No, that's Federal funding that was supposedly in the last budget, but nobody noticed it until it was "leaked" over the weekend. The article is quoted in the Trams thread

muzzamo
Legendary Member!
Posts: 1026
Joined: Tue Aug 21, 2007 4:44 pm

[U/C] Re: North-South Motorway

#2975 Post by muzzamo » Tue Sep 04, 2018 11:19 am

Don't think this video has been on posted here yet

how good is he
Legendary Member!
Posts: 1233
Joined: Thu Jan 24, 2013 1:26 am

[U/C] Re: North-South Motorway

#2976 Post by how good is he » Tue Sep 04, 2018 11:41 am

SBD, the proposed infrastructure funding [$7.6b Australia wide] was signed off by Turnbull to be announced prior to the next election [but leaked by the media prior].

User avatar
Norman
Donating Member
Donating Member
Posts: 6393
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: [U/C] Re: North-South Motorway

#2977 Post by Norman » Tue Sep 04, 2018 5:23 pm

how good is he wrote:SBD, the proposed infrastructure funding [$7.6b Australia wide] was signed off by Turnbull to be announced prior to the next election [but leaked by the media prior].
I'm not sure if this was to be/will be additional money to the $1.2b announced in the last budget, but there definitely was some money set aside previously.

User avatar
1NEEDS2POST
High Rise Poster!
Posts: 471
Joined: Tue Jun 26, 2018 5:01 pm

[U/C] Re: North-South Motorway

#2978 Post by 1NEEDS2POST » Tue Sep 04, 2018 8:37 pm

Since this will finish ahead of schedule, when will work start on the Pym Street to Regency Road section?

User avatar
Norman
Donating Member
Donating Member
Posts: 6393
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: North-South Motorway

#2979 Post by Norman » Tue Sep 04, 2018 8:53 pm

1NEEDS2POST wrote:
Tue Sep 04, 2018 8:37 pm
Since this will finish ahead of schedule, when will work start on the Pym Street to Regency Road section?
Not for at least another year. There needs to be a lot of planning work, consultation work, design work, property acquisition, tendering... actual construction will probably start in late 2019, starting with service relocation work, and major construction in 2020.

SBD
Super Size Scraper Poster!
Posts: 2526
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[U/C] Re: North-South Motorway

#2980 Post by SBD » Tue Sep 04, 2018 8:58 pm

Norman wrote:
Tue Sep 04, 2018 8:53 pm
1NEEDS2POST wrote:
Tue Sep 04, 2018 8:37 pm
Since this will finish ahead of schedule, when will work start on the Pym Street to Regency Road section?
Not for at least another year. There needs to be a lot of planning work, consultation work, design work, property acquisition, tendering... actual construction will probably start in late 2019, starting with service relocation work, and major construction in 2020.
I guess that depends on the definition of "work". There are a lot of engineers, draughters, real estate agents etc that would think they are "working" while doing that planning, consultation, design, property acquisition, tendering etc. If it is only "work" while people are playing with oversized Tonka toys, then you are right about it being over a year away.

how good is he
Legendary Member!
Posts: 1233
Joined: Thu Jan 24, 2013 1:26 am

[U/C] Re: North-South Motorway

#2981 Post by how good is he » Tue Sep 04, 2018 11:26 pm

Maybe after they finish Darlington (if the same company is chosen) the “workers” can start here.

User avatar
Norman
Donating Member
Donating Member
Posts: 6393
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: North-South Motorway

#2982 Post by Norman » Wed Sep 05, 2018 9:15 am

I've made another drive-through video for the Darlington project.

https://youtu.be/EGIBHU3ewIs

claybro
Super Size Scraper Poster!
Posts: 2378
Joined: Mon Jun 18, 2012 9:16 pm

[U/C] Re: North-South Motorway

#2983 Post by claybro » Wed Sep 05, 2018 2:12 pm

Norman wrote:
Tue Sep 04, 2018 8:53 pm
1NEEDS2POST wrote:
Tue Sep 04, 2018 8:37 pm
Since this will finish ahead of schedule, when will work start on the Pym Street to Regency Road section?
Not for at least another year. There needs to be a lot of planning work, consultation work, design work, property acquisition, tendering... actual construction will probably start in late 2019, starting with service relocation work, and major construction in 2020.
They've known about this section for how long already?

User avatar
Norman
Donating Member
Donating Member
Posts: 6393
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: [U/C] Re: North-South Motorway

#2984 Post by Norman » Wed Sep 05, 2018 2:27 pm

claybro wrote:
Norman wrote:
Tue Sep 04, 2018 8:53 pm
1NEEDS2POST wrote:
Tue Sep 04, 2018 8:37 pm
Since this will finish ahead of schedule, when will work start on the Pym Street to Regency Road section?
Not for at least another year. There needs to be a lot of planning work, consultation work, design work, property acquisition, tendering... actual construction will probably start in late 2019, starting with service relocation work, and major construction in 2020.
They've known about this section for how long already?
Sure, but design work, property acquisition and all that costs money. DPTI don't do that work, most of it is outsourced. No work starts until the government allocates money to it, that's why the budget has so many business cases in it.

Archer
High Rise Poster!
Posts: 152
Joined: Mon Jun 09, 2008 11:44 am

[U/C] Re: North-South Motorway

#2985 Post by Archer » Wed Sep 05, 2018 5:10 pm

There is also supposed to be a duplication of South Road from Seaford to Sellicks Beach with construction to start in 2019. While obviously not on the scale of the rest of the North south Corridor works, it's still a significant project with $305M allocated for stage one (Seaford to Aldinga Beach Road). The project page on the DPTI website is pretty sparse with just the project overview and benefits information. Does anyone have or know any more details about this project yet? When would we be likely to start seeing more information, given construction is supposed to start in 2019 (although probably late 2019 given it's September already)?