#1051 Post by Norman » Mon Jun 14, 2010 2:09 pm

They are doing some more work on the Noarlunga Line today, from what I saw mostly on the Daws Road and Marion Road bridges.

User avatar
Xaragmata
Super Size Scraper Poster!
Posts: 1613
Joined: Thu Jul 19, 2007 2:08 pm
Location: Adelaide / West
Contact:

Re: Electrification and Resleepering of TransAdelaide Networ

#1052 Post by Xaragmata » Tue Jun 15, 2010 2:22 pm

Substitute bus bay at Adelaide station:

Image


Image


Validators and sheep run:

Image


http://xaragmata.cable.nu/album/railway ... index.html

User avatar
AtD
VIP Member
VIP Member
Posts: 4581
Joined: Wed Jul 20, 2005 7:00 pm
Location: Sydney

Re: Electrification and Resleepering of TransAdelaide Networ

#1053 Post by AtD » Tue Jun 15, 2010 4:59 pm

Interesting. Thanks for that.

User avatar
Xaragmata
Super Size Scraper Poster!
Posts: 1613
Joined: Thu Jul 19, 2007 2:08 pm
Location: Adelaide / West
Contact:

Re: Electrification and Resleepering of TransAdelaide Networ

#1054 Post by Xaragmata » Tue Jun 22, 2010 5:12 am

Pics from Monday - works train on SG unloading sleepers between Hawker Street & Dudley Park:

Hawker Street:

Image

Image

Image


Ovingham:

Image

Image

Image

Image

Image

Image


Dudley Park:

Image

Image

Image

Image

Image


http://xaragmata.cable.nu/album/railway ... _8448.html


For anyone with nothing better to do, a slideshow of the album, with some video of work train crossing Torrens Road:


User avatar
Norman
Donating Member
Donating Member
Posts: 6422
Joined: Sun Mar 25, 2007 1:06 pm

Re: Electrification and Resleepering of TransAdelaide Networ

#1055 Post by Norman » Wed Jun 23, 2010 9:02 pm

Things are certainly moving quickly up there, thanks for the update.

RayRichards
High Rise Poster!
Posts: 107
Joined: Sun Jun 21, 2009 9:55 pm
Location: Glenelg South

Re: Electrification and Resleepering of TransAdelaide Networ

#1056 Post by RayRichards » Thu Jun 24, 2010 2:55 pm

On the Infrastructure website relating to this project. It mentioned it will be dealing with stormwater issues?? Will there be a concrete stormwater drain to be built running along side the new track work? On the champion photos taken from Xaragmata, there seems to be plenty of room along side the track area, even for a bike track.

Nearmap shows this to be possible?! (I like nearmap as you can tell! :mrgreen: )

If only a bridge overpass was to be built on Torrens Road while this stretch of track work was worked on. Surely this must be one of the next grade separation priorities?

Ray.

fabricator
Legendary Member!
Posts: 537
Joined: Mon Oct 27, 2008 9:13 pm

Re: Electrification and Resleepering of TransAdelaide Networ

#1057 Post by fabricator » Fri Jun 25, 2010 12:05 am

RayRichards wrote:On the Infrastructure website relating to this project. It mentioned it will be dealing with stormwater issues?? Will there be a concrete stormwater drain to be built running along side the new track work? On the champion photos taken from Xaragmata, there seems to be plenty of room along side the track area, even for a bike track.
Some small stormwater drains installed between the tracks at some stations.

Mainly they are referring to a stormwater drain at Dry Creek which is being replaced with a much larger version.
AdelaideNow: Now with 300% more Liberal Party hacks, at no extra cost.

User avatar
Xaragmata
Super Size Scraper Poster!
Posts: 1613
Joined: Thu Jul 19, 2007 2:08 pm
Location: Adelaide / West
Contact:

Re: Electrification and Resleepering of TransAdelaide Networ

#1058 Post by Xaragmata » Fri Jun 25, 2010 3:05 pm

RayRichards wrote:On the Infrastructure website relating to this project. It mentioned it will be dealing with stormwater issues?? Will there be a concrete stormwater drain to be built running along side the new track work? On the champion photos taken from Xaragmata, there seems to be plenty of room along side the track area, even for a bike track.

Nearmap shows this to be possible?! (I like nearmap as you can tell! :mrgreen: )

If only a bridge overpass was to be built on Torrens Road while this stretch of track work was worked on. Surely this must be one of the next grade separation priorities?

Ray.
At North Adelaide, they used about 30cm pipe between the tracks - I assume they just connect it to the existing storm water system. Any bike track would
need to allow for stanchions when electrification takes place, but there is a new path at Islington by the Palm Gardens site. The land for the Torrens Road
overpass was cleared about 20 years ago (or more?), but overpass was never built & is now an urban forest on the north side of Torrens Road.

User avatar
Xaragmata
Super Size Scraper Poster!
Posts: 1613
Joined: Thu Jul 19, 2007 2:08 pm
Location: Adelaide / West
Contact:

Re: Electrification and Resleepering of TransAdelaide Networ

#1059 Post by Xaragmata » Fri Jun 25, 2010 3:14 pm

Yesterday between Torrens and Hawker Street. Good progress on tracklaying and welding.

Image

Image

Image


North Adelaide

Image


Park Terrace

Image


Hawker Street

Image

Image


http://xaragmata.cable.nu/album/railway ... index.html

Nort
Super Size Scraper Poster!
Posts: 2213
Joined: Tue Feb 09, 2010 2:08 pm

Re: Electrification and Resleepering of TransAdelaide Networ

#1060 Post by Nort » Sat Jun 26, 2010 1:08 am

The speed of progress is impressive, just looking at this shot now though...
Xaragmata wrote:
Image
That's pretty damn wonky! I assume that isn't how the track actually ends up so how do they go about straightening it? I always assumed they would line up the sleepers before laying the track but do they do it like this first and then straighten it?

User avatar
jk1237
Donating Member
Donating Member
Posts: 1756
Joined: Wed Jan 17, 2007 11:22 pm
Location: Adelaide

Re: Electrification and Resleepering of TransAdelaide Networ

#1061 Post by jk1237 » Sat Jun 26, 2010 10:08 am

Nort wrote:
That's pretty damn wonky! I assume that isn't how the track actually ends up so how do they go about straightening it? I always assumed they would line up the sleepers before laying the track but do they do it like this first and then straighten it?
thats not too bad actually, you should have seen it when they relayed the Glenelg tramline. That was really wonky sleeper laying in some spots. However a big heavy and expensive machine (tamper or tampering or something) rolls down the track, and actually lifts the track slightly off the ground and adjusts the sleepers and whatnot, to make a perfect straight track.

great photos all around the site lately Xaragmata :D

User avatar
AtD
VIP Member
VIP Member
Posts: 4581
Joined: Wed Jul 20, 2005 7:00 pm
Location: Sydney

Re: Electrification and Resleepering of TransAdelaide Networ

#1062 Post by AtD » Sat Jun 26, 2010 11:05 am

Nort: A tamper on the Glenelg line. Pic by BillD
Image

bay transit
High Rise Poster!
Posts: 139
Joined: Wed Oct 17, 2007 8:30 pm

Re: Electrification and Resleepering of TransAdelaide Networ

#1063 Post by bay transit » Sat Jun 26, 2010 12:50 pm

I rode into town and back on Wednesday afternoon/evening on Flexities-it is noticeable that the ride has become "rocky" in a few spots also there are a few speed restrictions as well.
Overhead between Brighton Road and Moseley Square along Jetty Road Glenelg has been restrung with new "Light Rail" fittings as well it has now been staggered.
There is still a couple of late nights next week to tidy up and remove old poles

User avatar
Xaragmata
Super Size Scraper Poster!
Posts: 1613
Joined: Thu Jul 19, 2007 2:08 pm
Location: Adelaide / West
Contact:

Re: Electrification and Resleepering of TransAdelaide Networ

#1064 Post by Xaragmata » Sun Jun 27, 2010 3:44 pm

fabricator wrote:
RayRichards wrote:On the Infrastructure website relating to this project. It mentioned it will be dealing with stormwater issues?? Will there be a concrete stormwater drain to be built running along side the new track work? On the champion photos taken from Xaragmata, there seems to be plenty of room along side the track area, even for a bike track.
Some small stormwater drains installed between the tracks at some stations.

Mainly they are referring to a stormwater drain at Dry Creek which is being replaced with a much larger version.
For Ray - the drain & concrete sections are visible in Nearmap, alongside the Gawler line near the railcar depot. I guess the penrice stone train has
been replaced with heaps of trucks for the duration.

User avatar
Pistol
Legendary Member!
Posts: 1002
Joined: Sat Jul 01, 2006 5:46 pm
Location: Adelaide

Re: Electrification and Resleepering of TransAdelaide Networ

#1065 Post by Pistol » Sun Jun 27, 2010 10:06 pm

Rode under the Park Tce overpass today and noticed that they are using wooden sleepers on the inbound track for the length of the overpass.
However on the outbound track, they had concrete sleepers in the same location.

What would be the reason for this?