#541 Post by rev » Mon Sep 27, 2021 9:31 am

citywatcher wrote:
Sun Sep 26, 2021 10:42 am
dsriggs wrote:
MR_T wrote:
Sat Sep 25, 2021 10:57 am
What a joke this is. On hold again until April 22


Sent from my iPhone using Tapatalk
I mean, probably a good idea to wait until there's... y'know... tourists before you start building a hotel.
By the time you finish in about 2 to 3 years won't the tourists be back ? I mean no one will be able to stay there during construction.

Sent from my SM-A515F using Tapatalk
Why wouldnt locals be able to stay there when it's finished if borders are still closed? ie local tourism.

Patrick_27
Super Size Scraper Poster!
Posts: 2436
Joined: Tue Mar 05, 2013 4:41 pm
Location: Adelaide CBD, SA

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#542 Post by Patrick_27 » Mon Sep 27, 2021 2:30 pm

Be glad not to see this building go up, dog shit design compared to its predecessor.

crawf
Donating Member
Donating Member
Posts: 5523
Joined: Thu Feb 16, 2006 7:49 pm
Location: Adelaide

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#543 Post by crawf » Mon Sep 27, 2021 7:51 pm

Patrick_27 wrote:
Mon Sep 27, 2021 2:30 pm
Be glad not to see this building go up, dog shit design compared to its predecessor.
Agreed. Could be a blessing this keeps getting delayed.

Previous proposal was far better.

User avatar
gnrc_louis
Legendary Member!
Posts: 875
Joined: Sat Nov 10, 2018 2:04 pm
Location: Adelaide

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#544 Post by gnrc_louis » Fri Nov 12, 2021 10:03 pm

There's a paywalled Advertiser article about this one: https://www.adelaidenow.com.au/subscrib ... our=append

User avatar
Algernon
Super Size Scraper Poster!
Posts: 1556
Joined: Sat Jul 09, 2005 9:46 pm
Location: Moravia

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#545 Post by Algernon » Fri Nov 12, 2021 10:49 pm

gnrc_louis wrote:
Fri Nov 12, 2021 10:03 pm
There's a paywalled Advertiser article about this one: https://www.adelaidenow.com.au/subscrib ... our=append
The usual, this time the excuse is Covid.

User avatar
gnrc_louis
Legendary Member!
Posts: 875
Joined: Sat Nov 10, 2018 2:04 pm
Location: Adelaide

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#546 Post by gnrc_louis » Sun Nov 14, 2021 10:56 pm

Hyatt development delayed again due to Covid

Major city projects are facing lengthy delays due to Covid, including the new $160m Hyatt, which is now expected to open much later than originally planned.
Renato Castello and Giuseppe Tauriello

November 12, 2021 - 2:52PM

Major hotel developments, including a new $160m Hyatt in the CBD, are facing lengthy delays due to Covid, with developers eager for the return of interstate and international travel before committing to projects.

Construction of the Hyatt will start in the second half of next year, the company and the project’s developer say, with the hotel due to open in 2025, two years later than first anticipated.

Plans for a 17-storey hotel on Wright St have also been pushed back by developer Kite to October next year, close to two years after initially planned, while a $48m Travelodge on Bentham St secured a second 12-month extension to its development approval in July.

A spokesman for Hyatt, which is marking its return to Adelaide with a new 285-room building on the corner of Gawler Place and Pirie St, said demolition works would begin in the second half of 2022.

The state’s planning authority gave the 21-storey five-star hotel, which will replace an existing local heritage-listed bank building, planning consent in August 2020.

Project director Robert Lee of CES Pirie Hotel had previously anticipated site works would begin in the first half of 2021.

But in a joint statement Mr Lee and Hyatt said the development timeline had been reworked due to Covid. Instead they are aiming to secure final development approval with Adelaide City Council in the first half of next year paving the way for demolition of the existing bank building.

“CES Pirie Hotel and Hyatt remain committed to launching Hyatt Regency Adelaide which will mark Hyatt’s return to the city when the hotel opens in 2025,” the company’s statement said.
Artist's impressions of the $200m GPO Hotel development, which began earlier this year. Picture: Supplied by Greaton
Artist's impressions of the $200m GPO Hotel development, which began earlier this year. Picture: Supplied by Greaton

Despite the uncertainty caused by the pandemic, construction of several new hotels has begun in recent months including the $45m Vibe hotel on Flinders St, the $200m Marriott hotel at the GPO site and the $35m TRYP by Wyndham hotel on Pulteney St.

Last week Canberra-based developer Doma Group took over the Metters building site on North Tce, between Oaks Horizons and Oaks Embassy, with plans to launch its Little National Hotel network into Adelaide.

The project is still in the design phase, but it is expected to include about 200 rooms, an exclusive gym, library and lounge for guests, and a rooftop bar open to the public.

A development application is expected to be lodged early next year ahead of the commencement of construction by September.

Adelaide developer Kite, formerly Starfish Developments, is also expected to start work on its 93-room MH Hotel project in Port Adelaide’s Marine and Harbours building by the middle of next year, and is planning to add an additional 60 rooms in a second stage.

Kite managing director Damon Nagel said the area was in need of extra hotel accommodation given the shipbuilding projects ramping up at the nearby Osborne shipyards.

“We’re in documentation now, we’ll go out to tender in February and we’re looking to start work in July on the main building,” he said.

“And then we’re in planning for another 60 rooms in a separate building right next door. We’ve designed it with a vibe of the old wool stores – it’s a warehouse-style looking building.”

Mr Nagel said plans for the Wright St hotel, which would be operated by Punthill Apartment Group and would include about 100 rooms, would restart after Easter with construction expected to commence by October.

HiTouch
Legendary Member!
Posts: 729
Joined: Thu Feb 13, 2014 10:40 pm

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#547 Post by HiTouch » Fri Nov 19, 2021 9:57 am

20-22 Currie St vibes with this one.

Delay, Recession, Delay, "we remain committed", 12 month delay, never happens.

If this happens, I'll be surprised.

SBD
Super Size Scraper Poster!
Posts: 2524
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#548 Post by SBD » Mon Nov 22, 2021 8:56 pm

Algernon wrote:
Fri Nov 12, 2021 10:49 pm
gnrc_louis wrote:
Fri Nov 12, 2021 10:03 pm
There's a paywalled Advertiser article about this one: https://www.adelaidenow.com.au/subscrib ... our=append
The usual, this time the excuse is Covid.
Who actually pays for the build? Adelaide and Australia are starting to look a little less threatened, but if the global company has to pay for the build, perhaps its global cash flow is sufficiently limited to make it necessary to delay any capital expenditure it can. Deferring the build so it can open about when the company expects the market to recover is good sense, there are plenty of hotels in Adelaide for the current market.

Tom's Court seems to have timed its completion perfectly. I don't think it has ever been open as a "normal" hotel, but has been fully booked throughout the pandemic, with free SA advertising thrown in.

User avatar
gnrc_louis
Legendary Member!
Posts: 875
Joined: Sat Nov 10, 2018 2:04 pm
Location: Adelaide

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#549 Post by gnrc_louis » Mon Jan 15, 2024 1:00 pm

Sounds like this is getting another redesign: https://indaily.com.au/news/local/2024/ ... att-hotel/

Ben
VIP Member
VIP Member
Posts: 7479
Joined: Mon Dec 19, 2005 11:46 am
Location: Adelaide

[APP] Re: 51 Pirie Street | 94m | 21 Levels | Hyatt

#550 Post by Ben » Mon Jan 15, 2024 1:25 pm

gnrc_louis wrote:
Mon Jan 15, 2024 1:00 pm
Sounds like this is getting another redesign: https://indaily.com.au/news/local/2024/ ... att-hotel/
I hope they incorporate the facade but not very confident.