Recent progress:
The 'tent' has been moved around again and you can just see an excavator working inside. Demolition of the old retaining walls is also underway.

Image
Listy
High Rise Poster!
Posts: 104
Joined: Sat Oct 01, 2016 11:07 pm

[SWP] Re: SAHMRI Stage 2

Post by Listy »

The tent has been moved (perhaps for the last time - it looks like its being dismantled), revealing the excavation work that was taking place underneath. The old retaining walls are being taken apart - they'll probably remove the remaining bits once the crane is gone.

Image
User avatar
rev
SA MVP (Most Valued Poster 4000+)
Posts: 4615
Joined: Sat Nov 11, 2006 12:14 pm

[SWP] Re: SAHMRI Stage 2

Post by rev »

Ok so I was way off with my idea that it's for politicians to hold a media photo shoot :hilarious:

What sort of excavation requires a marquee on top? Surely not contaminated soil?
Perhaps there were Aboriginal remains there? Wasn't the riverbank meant to be some sacred site for them or something? I remember something years ago
urban
Legendary Member!
Posts: 583
Joined: Thu Apr 12, 2007 10:59 am
Location: City of Unley

[SWP] Re: SAHMRI Stage 2

Post by urban »

Highly likely that it was contaminated soil. A common method of limiting the risk is to dig up the contaminated soil, wrap it in plastic and bury it below a new building. This prevents the contamination from leaking into surrounding soils and building over the top of it prevents it being accidently dug up.
EBG
Super Size Scraper Poster!
Posts: 2487
Joined: Fri Jul 12, 2013 10:49 pm

[SWP] Re: SAHMRI Stage 2

Post by EBG »

Update 22/8/20 yes the large tent/shed and mobile crane have gone work now on burying heaps of dirt. Please click on picture for bigger.
Attachments
20200822_sahmri 2.jpg
Growl3r
Sen-Rookie-Sational
Posts: 3
Joined: Wed Aug 05, 2020 8:07 am

[SWP] Re: SAHMRI Stage 2

Post by Growl3r »

EBG wrote:
Sat Aug 22, 2020 10:33 pm
Update 22/8/20 yes the large tent/shed and mobile crane have gone work now on burying heaps of dirt. Please click on picture for bigger.
It looks to be they are building a piling platform
EBG
Super Size Scraper Poster!
Posts: 2487
Joined: Fri Jul 12, 2013 10:49 pm

[SWP] Re: SAHMRI Stage 2

Post by EBG »

It appears that the soil remediation phase has finished. Most of the heaps of dirt have ether been buried or removed and a clean layer of compacted fill has been laid awaiting the next phase of construction . Pictures 20/9/2020.
Attachments
20200920_sam 1.jpg
20200920_ sam 2.jpg
NTRabbit
High Rise Poster!
Posts: 205
Joined: Fri Dec 28, 2018 10:00 pm

[SWP] Re: SAHMRI Stage 2

Post by NTRabbit »

Seems kind of odd to fill the hole back in when they have to dig right through it again to make the deep concrete basement for the proton therapy equipment
Last edited by NTRabbit on Sun Sep 20, 2020 10:01 pm, edited 1 time in total.
EBG
Super Size Scraper Poster!
Posts: 2487
Joined: Fri Jul 12, 2013 10:49 pm

[SWP] Re: SAHMRI Stage 2

Post by EBG »

I agree.
EBG
Super Size Scraper Poster!
Posts: 2487
Joined: Fri Jul 12, 2013 10:49 pm

[SWP] Re: SAHMRI Stage 2

Post by EBG »

I agree.
User avatar
SouthAussie94
High Rise Poster!
Posts: 377
Joined: Tue Mar 27, 2012 10:03 pm
Location: Southern Suburbs

[SWP] Re: SAHMRI Stage 2

Post by SouthAussie94 »

NTRabbit wrote:
Sun Sep 20, 2020 9:35 pm
Seems kind of odd to fill the hole back in when they have to dig right through it again to make the deep concrete basement for the proton therapy equipment
They need a piling rig on site to stabilise the ground around the future basement before they can start excavating the dirt for the basement. A piling rig needs a pretty even and stable surface to work on, hence they've filled the hole in.
"All we are is bags of bones pushing against a self imposed tide. Just be content with staying alive"

Views and opinions expressed are my own and don't necessarily reflect the views or opinions of any organisation of which I have an affiliation
Listy
High Rise Poster!
Posts: 104
Joined: Sat Oct 01, 2016 11:07 pm

[SWP] Re: SAHMRI Stage 2

Post by Listy »

Definitely getting closer to the next construction phase. Even with the filling & leveling of the holes that were dug to remove contaminated soil etc, there's still a fairly large drop (about 5m) from the front of the site to the back corner, so there might not be much more re-excavation required. The sub ground areas will be below North Terrace level but still mostly at street level for George St. due to that relative difference in elevation.

Image
ndru_01
Sen-Rookie-Sational
Posts: 2
Joined: Mon Mar 01, 2010 3:18 pm

[SWP] Re: SAHMRI Stage 2

Post by ndru_01 »

They’ve only just finished removing the old train control centre. Excavation for piling for 3 storeys underground for the proton therapy bunker is the next stage, which will take months.


Sent from my iPad using Tapatalk
Listy
High Rise Poster!
Posts: 104
Joined: Sat Oct 01, 2016 11:07 pm

[SWP] Re: SAHMRI Stage 2

Post by Listy »

it looks like some some rebar piling cages have appeared on the site (on the right hand side). A curious trench has also been dug around the North Terrace edge and filled with what look like foam blocks which are being cemented in place. A vibration suppression strategy maybe?

Image
Growl3r
Sen-Rookie-Sational
Posts: 3
Joined: Wed Aug 05, 2020 8:07 am

[SWP] Re: SAHMRI Stage 2

Post by Growl3r »

OMG.jpg
OMG.jpg (8.49 KiB) Viewed 1513 times