[U/C] Re: Ovingham Level Crossing Removal | $231m

#166 Post by PD2/20 » Tue Nov 23, 2021 5:33 pm

Spotto wrote:
Mon Nov 22, 2021 11:52 pm
On the plus side, with how far behind the Gawler line electrification is, the construction of this overpass isn’t causing additional line closures. :lol:
Could it be that the Ovingham work was a factor in the indefinite extension of the line closure from the last stated resumption date of November 2021? The lift yesterday required possession of the track adjacent to the new girders. Similar possessions will be needed this week for the second pair of eastern girders and for the spans over the track which I understand will be installed next week.

ralmin
Gold-Member ;)
Posts: 69
Joined: Tue Dec 15, 2009 7:38 pm

[U/C] Re: Ovingham Level Crossing Removal | $231m

#167 Post by ralmin » Thu Nov 25, 2021 12:13 am

The freight line surely remains open most of the time. If so the Ovingham level crossing removal project would need occasional line closures to prevent freight trains passing through when they need to work around/over the line.

User avatar
Llessur2002
Super Size Scraper Poster!
Posts: 2068
Joined: Mon Mar 17, 2014 4:59 pm
Location: Inner West

[U/C] Re: Ovingham Level Crossing Removal | $231m

#168 Post by Llessur2002 » Thu Nov 25, 2021 11:31 pm

From today:

Image

SBD
Super Size Scraper Poster!
Posts: 2524
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[U/C] Re: Ovingham Level Crossing Removal | $231m

#169 Post by SBD » Fri Nov 26, 2021 12:07 pm

ralmin wrote:
Thu Nov 25, 2021 12:13 am
The freight line surely remains open most of the time. If so the Ovingham level crossing removal project would need occasional line closures to prevent freight trains passing through when they need to work around/over the line.
I don't think the line is operated at capacity so it is possible there are sufficient gaps to not interrupt the freight? It might be closed for blocks of four-six hours, not days/weeks at a time.

EBG
Super Size Scraper Poster!
Posts: 2956
Joined: Fri Jul 12, 2013 10:49 pm

[U/C] Re: Ovingham Level Crossing Removal | $231m

#170 Post by EBG » Sat Dec 04, 2021 3:15 pm

Some pictures from Saturday 4/12/212- looking from west to east.
Attachments
20211204_Ove 1.jpg
20211204_Ove 2.jpg
20211204_Ove 3.jpg

VLtom
Sen-Rookie-Sational
Posts: 33
Joined: Fri Feb 19, 2021 6:11 pm
Location: The Adelaide O-Bahn
Contact:

[U/C] Re: Ovingham Level Crossing Removal | $231m

#171 Post by VLtom » Sat Dec 04, 2021 5:43 pm

EBG wrote:
Sat Dec 04, 2021 3:15 pm
Some pictures from Saturday 4/12/212- looking from west to east.
Real shame about the lack of future proofing for double stacked freight trains, with how low this bridge will be and limited options to lower the tracks through this section

PD2/20
High Rise Poster!
Posts: 364
Joined: Sun Feb 23, 2014 2:32 pm

[U/C] Re: Ovingham Level Crossing Removal | $231m

#172 Post by PD2/20 » Sat Dec 04, 2021 7:44 pm

VLtom wrote:
Sat Dec 04, 2021 5:43 pm
Real shame about the lack of future proofing for double stacked freight trains, with how low this bridge will be and limited options to lower the tracks through this section
How does this line up with Norman's post earlier in this thread? There are a number of locations such as KIlburn, Greenfields and Parafield Gardens where double stacked trains on the ARTC line pass under overhead gantries.
Last edited by PD2/20 on Sat Dec 04, 2021 7:56 pm, edited 1 time in total.

PD2/20
High Rise Poster!
Posts: 364
Joined: Sun Feb 23, 2014 2:32 pm

[U/C] Re: Ovingham Level Crossing Removal | $231m

#173 Post by PD2/20 » Sat Dec 04, 2021 7:46 pm

EBG wrote:
Sat Dec 04, 2021 3:15 pm
Some pictures from Saturday 4/12/212- looking from west to east.
The girder lift planned for this afternoon was postponed until Monday because of wind conditions.

SBD
Super Size Scraper Poster!
Posts: 2524
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[U/C] Re: Ovingham Level Crossing Removal | $231m

#174 Post by SBD » Sat Dec 04, 2021 10:31 pm

PD2/20 wrote:
Sat Dec 04, 2021 7:44 pm
VLtom wrote:
Sat Dec 04, 2021 5:43 pm
Real shame about the lack of future proofing for double stacked freight trains, with how low this bridge will be and limited options to lower the tracks through this section
How does this line up with Norman's post earlier in this thread? There are a number of locations such as KIlburn, Greenfields and Parafield Gardens where double stacked trains on the ARTC line pass under overhead gantries.
The bridge appears to be high enough to go above the catenary wires for the electric trains. I have no idea what clearances are needed for double containers, nor for the electrification.

UPDATE: DPTI shows the electric wire is 5200mm above the track, and the poles are 8000mm high. https://www.dpti.sa.gov.au/__data/asset ... ow_Res.pdf

Several sources seem to suggest that clearance required for double stacked containers is 7100mm above the rails. For example https://www.australasiantransportresear ... Leviny.pdf seems to indicate that is the dynamic envelope height required, not just the height of the train.

I think that means they should fit.

VLtom
Sen-Rookie-Sational
Posts: 33
Joined: Fri Feb 19, 2021 6:11 pm
Location: The Adelaide O-Bahn
Contact:

[U/C] Re: Ovingham Level Crossing Removal | $231m

#175 Post by VLtom » Fri Dec 10, 2021 8:07 am

SBD wrote:
Sat Dec 04, 2021 10:31 pm
PD2/20 wrote:
Sat Dec 04, 2021 7:44 pm
VLtom wrote:
Sat Dec 04, 2021 5:43 pm
Real shame about the lack of future proofing for double stacked freight trains, with how low this bridge will be and limited options to lower the tracks through this section
How does this line up with Norman's post earlier in this thread? There are a number of locations such as KIlburn, Greenfields and Parafield Gardens where double stacked trains on the ARTC line pass under overhead gantries.
The bridge appears to be high enough to go above the catenary wires for the electric trains. I have no idea what clearances are needed for double containers, nor for the electrification.

UPDATE: DPTI shows the electric wire is 5200mm above the track, and the poles are 8000mm high. https://www.dpti.sa.gov.au/__data/asset ... ow_Res.pdf

Several sources seem to suggest that clearance required for double stacked containers is 7100mm above the rails. For example https://www.australasiantransportresear ... Leviny.pdf seems to indicate that is the dynamic envelope height required, not just the height of the train.

I think that means they should fit.
That would be the case if the pole was completely under the the bottom of the bridge, but it is not. More recent photos show how the catenary pole is placed between the bridge girders to only give clearance to the wires and their supporting structure. The pole was specially modified (return and earth wires have been lowered from their usual position) to fit under the bridge and so the catenary doesn't have to actually be attached to the bridge itself. This means there will probably be 5-6m clearance on the ARTC tracks, which is more than disappointing but hardly surprising. You're right about 7.1 being the envelope required though, the actual maximum height for ARTC trains is 6.5m from memory. I think regardless it's safe to say Adelaide will never get double stacked freight on the south line, when Inland Rail opens in by 2027 (Melbourne - Parkes section should be done a few years earlier then that) most freight Melbourne - Perth will go via Parkes not Adelaide, except maybe some superfreighter stuff. Getting double stacked freight shouldn't be a massive priority really (and the feds probably wouldn't want to fund it), and there are other improvements that should and can be made to that line regardless, but it'll still be a missed opportunity.

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2586
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[U/C] [U/C] Re: Ovingham Level Crossing Removal | $231m

#176 Post by ChillyPhilly » Fri Dec 10, 2021 8:16 am

Double stacked freight doesn't even fit under the Park Terrace bridge, so why would it be needed for the Ovingham crossing? This would need to be amended first.

Ideally, we should be removing freight from entering Adelaide via the Hills, and instead constructing a new entry that is more efficient.

The ARTC line is a significant barrier in some areas of Adelaide, and inhibits full use/better development along metropolitan passenger lines.

Freight can still enter from the north.
Our state, our city, our future.

All views expressed on this forum are my own.

PD2/20
High Rise Poster!
Posts: 364
Joined: Sun Feb 23, 2014 2:32 pm

[U/C] Re: [U/C] Re: Ovingham Level Crossing Removal | $231m

#177 Post by PD2/20 » Fri Dec 10, 2021 11:56 am

ChillyPhilly wrote:
Fri Dec 10, 2021 8:16 am
Double stacked freight doesn't even fit under the Park Terrace bridge, so why would it be needed for the Ovingham crossing? This would need to be amended first.

Ideally, we should be removing freight from entering Adelaide via the Hills, and instead constructing a new entry that is more efficient.

The ARTC line is a significant barrier in some areas of Adelaide, and inhibits full use/better development along metropolitan passenger lines.

Freight can still enter from the north.
The ARTC standards for the DIRN (Defined Interstate Rail Network), which Melbourne-Adelaide -Crystal Brook is part of, specifies double stacking clearances for new structures but not for existing structures. This makes sense as bridges are long lived assets and allows for eventual deployment of double stacking south of Islington Terminal.

The ARTC track under Park Terrace is visibly lower (~0.5m?) than the DIT tracks.

User avatar
Norman
Donating Member
Donating Member
Posts: 6392
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: Ovingham Level Crossing Removal | $231m

#178 Post by Norman » Sat Dec 18, 2021 7:10 pm

Almost all of the beams have now been installed.

Image

Image

Image

Image

marbles
Gold-Member ;)
Posts: 62
Joined: Sun Feb 23, 2020 4:22 pm

[U/C] Re: Ovingham Level Crossing Removal | $231m

#179 Post by marbles » Sun Dec 19, 2021 11:59 am

that bridge dont look too high, look at the height of the truck to the bridge. gotta get trains under there

but yes probs just the camera angle

so the obvious reply is..."yea just the camera angle"

ralmin
Gold-Member ;)
Posts: 69
Joined: Tue Dec 15, 2009 7:38 pm

[U/C] Re: Ovingham Level Crossing Removal | $231m

#180 Post by ralmin » Sun Dec 19, 2021 2:24 pm

This level crossing replacement seems to be coming along quite quickly. I was surprised to see a sign saying completion date March 2023.

Compared with at the overpass installation for R2P at Regency Road, once the bridge went in, it seemed to open to traffic within just a month or two.

On the other hand this project still has 15 months to go. There must be a lot more work involved after the bridge goes in.