Finally got a decent day off to have a good look at the works along the Noarlunga Line today. Things have moved along very quickly since i last had a look. The track is all laid and ballasted from Clarence Park to the Sturt River Bridge now.With the only piece missing between East Ave and Goodwood station now (The Underpass site) The Tamper's & Ballast Regulator were working in the Marion Station area today.
Electrification works have gotten as far as Woodlands Park, with a few missing poles over Marion/Daws rd embankments and on the Up line between the Sturt river Bridge and Marion Station.
A few photos from today's works.
Tamper 1 on the Marion Rd approach Embankment.

Tamper 2 @ Marion station.

Ballast Regulator @ Ascot Park

Looking Back towards Ascot Pk from Sixth ave crossing

Re-enforcing for the Overhead support poles @ Edwardstown.

Not Really part of the Noarlunga Line, But, As part of the Goodwood Grade Seperation Project. A new loop is being built between Goodwood and Millswood on the Belair Line.

New style hollow Sleeper for the point rodding to pass through.

And a Relic form the Past, The Former Millswood Station still reasonably intact.